Work is progressing on the townhouses located on lots 7 & 8. The drywall has been completed and the trim package will arrive on Friday of this week. The families are looking forward to painting, but may have to wait until it warms up a bit! Temperatures are supposed to drop this week, but we expect painting to begin within the next week.
The walls and roof trusses are in place on lots 9 & 10. Work will continue on the roof this week, and should it should be in place by the end of the week to get ready for shingles.
We also have the foundation poured for lots 15 & 16, so we can expect a delivery for those 2 units very soon.
In the next few weeks, we will have 6 more units completed, which will put us more than half-way through Phase I. These future homeowners are getting very excited about moving into their new houses.
We can use help with painting, volunteer transportation, meals, and construction. If anyone would like to volunteer, please contact Helen Ickes at 423 949-4074. We appreciate all the support from the local community, and look forward to continuing this project.
Tuesday, January 13, 2009
Subscribe to:
Post Comments (Atom)
No comments:
Post a Comment