We have been very busy at the Village the last few weeks. The roof and plumbing rough-in are completed for lots 1 & 2. Last week, we began installing the soffits and vinyl. This week's schedule includes finishing up the siding, and beginning on the electrical roughin. The insulation and sheetrock will arive next week.
We are also progressing on lots 17 and 18. The wall panels and roof trusses are in place. The roof should be in place by the end of the week.
The weather has been cooperating a little more the last few days, so we hope to proceed as planned. Our first 2 units should be completed very soon, with 2 more to follow.