The family inspecting progress on lot 17
Everyone is working hard to move toward a finish date of late October. We expect to have our first 4 homeowners moved in very soon!
Insulation for lots 1 & 2 has been completed, and the drywall will be finished by Friday. The inside trimout, including cabinets and flooring, is to be delivered on Friday. We have generous volunteers from the Dunlap Seventh Day Adventist Church who will begin painting lot 1 on Sunday. The outside of these 2 units is looking good. Most of the backfilling has taken place, and we are waiting now for the topsoil so we can begin planning when the sidewalk and landscaping will be completed.
Insulation work on lots 17 & 18 is also scheduled for this week, with drywall to follow on Thursday.
Sewer pump wiring and approval is to be scheduled in the next few days. The final plat reading by the city is scheduled for 10/27. Once that is approved and filed, we can close on the first 4 units!!
A special thanks to the Dunlap Master Gardners and Sophia Gabalski. They have offered to assist with the landscaping. Since fall is a great time to plant, we expect to see grass, bushes, and a few trees very soon.
Our plans for the next 2 units are taking place, on lots 7 & 8. Footings will be poured in the next week (if it stays dry!) and the house package will be delivered soon after that.
Our homeowners are getting very excited. We appreciate your visits to the site to check out the work and provide some moral support. In the near future, you won't have to drive to visit, but can just step outside & walk to our office. We are looking forward to the completion of Phase I with 15 homeowners in place. Then comes Phase II.
If anyone is interested in volunteering for this project, please contact Helen Ickes. She now has an office number at the construction office - 423 949-4074. We have some painting opportunities coming up soon, and can still use help with meals.